Port Keats Road and Saddle Rail Creek Bridge Upgrades

About

The Australian Government and Northern Territory Government are upgrading 11.7 kilometres of Port Keats Road at the Saddle Rail Creek to improve flood immunity and safety for road users.

The upgrades will include:

  • Construction of a new 45 metre (3 x 15 metre spans) two-lane bridge over Saddle Rail Creek.
  • Upgrade of 11.7 kilometres of road to a two-lane sealed standard including raised embankments, four flood ways, and five culvert crossings.

Works will commence late July-2020 and are expected to be completed by mid-2021.

Saddle Rail Creek bridge works

Contact

Project Manager: Jay Brewster-O'brien
Email: jay.brewster-o’brien@nt.gov.au

Last updated: 17 July 2020