Enabling infrastructure for Holtze development

The Department of Infrastructure, Planning and Logistics (DIPL) will be starting construction of the enabling and public infrastructure to support the release of urban residential land in Holtze.

Works will include targeted site clean-up, construction of road and intersection upgrades, storm water drainage; electrical, water and sewer reticulation; landscaping and lighting.

Works will be staged and are expected to be completed as follows:

Site clean-up

Tender awarded Friday 26 April, 2024. Works are expected to commence May 2024 and be completed July 2024.

Part A enabling Infrastructure

Tender has been released Monday 29 April, 2024. Works are expected to commence mid in 2024 and be completed by late 2025 (weather permitting).

Part B enabling Infrastructure

These works are currently in design and construction is expected to commence in mid-2025 following a tender process.

Additional Infrastructure

Further works for Greater Holtze will be delivered in future stages, subject to outcomes of ongoing planning work.

DIPL’s work is guided by and subject to the Northern Territory Planning Commission’s Holtze to Elizabeth River Subregional Land Use Plan and the Greater Holtze Area Plan.

Communication with stakeholders including land owners, businesses and residents will be ongoing throughout construction.

For further information about the project, please contact Hotline 1800 920 260 or email communications.dipl@nt.gov.au.

Holtze and Kowandi enabling infrastructure

The Department is currently in the negotiation phase of the Holtze Land Release RFP process. The RFP process is expected to be concluded shortly.

The successful Developer for the Holtze Land Release will be required to obtain planning approval through the Development Consent Authority, providing an opportunity for the public to comment on the proposed development.