Civil consultancy procurement plan

The consultancy procurement plan below is updated monthly.

Dates are estimates and are subject to change without notice.

Key:

  • estimated date (Est)
  • actual date (Act).

Note the following:

  • remote contracts will be subject to access to the remote community
  • COVID-19 border restrictions may also impact tender dates.

The table below is accurate as of 11 May 2022.

Region Program Project description Tier Advertising target Advertising period (weeks) Tender committal
Alice Springs Cyclical Maintenance Alice Springs Region - Road Inspections and Defects Recording and Asset Data Collection for a Period of 36 Months * Tier 4 $500,000 - 5M Act Nov-21 4 Act May-22
Darwin Cyclical Maintenance Darwin Region - Road Inspections and Defects Recording and Asset Data Collection for a Period of 36 Months * Tier 4 $500,000 - 5M Act Nov-21 4 Est May-22
Darwin Consultancy Panel Environmental Consultancy Tier 3 $100,000 - $500,000 Act Aug-21 4 Est May-22
Darwin Consultancy Weddell Freeway - Planning Study Tier 4 $500,000 - $5M Act Dec-21 8 Act Apr-22
Darwin Capital Works Design and Contract Management - Jabiru Road Upgrade (Kakadu National Park) Tier 3 $100,000 - $500,000 Est May-22 4 Est Sep-22
Darwin/Alice Springs Minor Works Darwin/Alice Springs - Bus Stop Roadmap to DDA Compliance Consultancy Tier 3 $100,000 - $500,000 Est May-22 4 Est Jul-22
Katherine Cyclical Maintenance Katherine Region - Road Inspections and Defects Recording and Asset Data Collection for a Period of 36 Months * Tier 4 $500,000 - 5M Act Nov-21 4 Est May-22
Katherine Minor Works Wollogorang Road - Design to Upgrade Foelsche River 70 kilometres and Wearyan River 55 Kilometres Crossing Tier 3 $100,000 - $500,000 Act Feb-22 2 Est May-22
Katherine Capital Works Survey and Design - Central Arnhem Road - Priority Package 3 Tier 3 $100,000 - $500,000 Est Sep-22 4 Est Dec-22
Katherine Capital Works Design and Contract Management - Gas Industry Roads Tier 3 $100,000 - $500,000 Est Dec-22 6 Est Mar-23
Katherine Consultancy Numbulwar - Phelps Crossing Road Tier 3 $100,000 - $500,000 Est May-22 3 Est Jun-22
Tennant Creek Cyclical Maintenance Tennant Region - Road Inspections and Defects Recording and Asset Data Collection for a Period of 36 Months * Tier 4 $500,000 - 5M Act Nov-21 4 Est May-22
Tennant Creek Consultancy Design and Document - Stuarty Highway/Warrego Road and Kaczinky Road Intersection Upgrade Tier 3 $100,000 - $500,000 Est May-22 3 Est Jul-22

Last updated: 12 May 2022