Building services procurement plan
The procurement plan is updated monthly, dates are estimates and are subject to change without notice.
Key:
- estimated date (Est)
- actual date (Act).
Note: Remote contracts will be subject to access to the remote community.
Region | Electorate | Program | Project description | Tier | Advertising target | Advertising period (weeks) | Tender committal |
---|---|---|---|---|---|---|---|
Alice Springs | Araluen | Capital Works | ASH - Hybrid Operating Theatre - Consultancy | Tier 3 ($100 000 - $500,000) | Est Apr 21 | 4 | Est Jun 21 |
Alice Springs | Araluen | Capital Works | ASH - Hybrid Operating Theatre - Construction | Tier 3 ($100 000 - $500,000) | Est Dec 21 | 6 | Est Mar 22 |
Alice Springs | Araluen | Minor Works | ASH - Outpatients Area 1A ENT Upgrade | Tier 3 $100,000 - $500,000 | Est Mar 21 | 4 | Est May 21 |
Alice Springs | Braitling | Capital Works | Shade Structures and Cooling Initiatives - City Deals Alice Springs | Tier 4 ($500 000-$5 million) | Act Dec 21 | 6 | Est Apr 21 |
Alice Springs | Braitling | Capital Works | Lighting Upgrades - City Deals Alice Springs | Tier 3 ($100 000 - $500,000) | Act Oct 20 | 6 | Est Apr 21 |
Alice Springs | Braitling | Capital Works | Activation Zone - City Deals Alice Springs | Tier 3 ($100 000 - $500,000) | Act Oct 20 | 4 | Est Apr 21 |
Alice Springs | Braitling | Minor Works | Jalistan House OPG Office Modifications and Soundproofing | Tier 3 $100,000 - $500,000 | Est Mar 21 | 4 | Est May 21 |
Alice Springs | Gwoja | Capital Works | SWAN Infrastructure Investment - Laramba School | Tier 3 ($100 000 - $500,000) | Est Mar 21 | 4 | Est May 21 |
Alice Springs | Gwoja | Capital Works | Mbunghara School - Playground Equipment | Tier 3 ($100 000 - $500,000) | Est Mar 21 | 4 | Est May 21 |
Alice Springs | Gwoja | Minor Works | Finke Gorge NP - Kalarranga Walk Redevelopment | Tier 3 ($100 000 - $500,000) | Est Apr 21 | 4 | Est Jun 21 |
Alice Springs | Gwoja | Minor Works | Mount Allan School - Refurbish Classroom & Ablutions | Tier 3 $100,000 - $500,000 | Est Mar 21 | 4 | Est May 21 |
Alice Springs | Namatjira | Capital Works | SWAN Infrastructure Investment - Harts Range School | Tier 3 ($100 000 - $500,000) | Est Apr 21 | 4 | Est Jun 21 |
Alice Springs | Namatjira | Capital Works | Construction - West Macdonnell National Park - Adventure Cycling Track - Trail | Tier 5 $5million and Greater | TBA | 4 | TBA |
Alice Springs | Namatjira | Capital Works | Construction - West Macdonnell National Park - Adventure Cycling Track - Camp | Tier 4 ($500 000-$5 million) | TBA | 6 | TBA |
Alice Springs | Namatjira | Capital Works | Construction - West Macdonnell National Park - Adventure Cycling Track - Interp Signage | Tier 4 ($500 000-$5 million) | TBA | 6 | TBA |
Alice Springs | Namatjira | Capital Works | Watarrka National Park - Iconic 5 Day Walking Track | Tier 5 $5million and Greater | TBA | 4 | TBA |
Alice Springs | Namatjira | Minor Works | Simpsons Gap Toilet Block Upgrade | Tier 3 $100,000 - $500,000 | Act Mar 21 | 4 | Est May 21 |
Alice Springs | Namatjira | Minor Works | ASTS Irrigation Upgrade | Tier 3 $100,000 - $500,000 | Act Jan 21 | 4 | Est Apr 21 |
Alice Springs | Namatjira | Minor Works | ASCC Secure Entrance | Tier 3 $100,000 - $500,000 | Est Aug 21 | 4 | Est Oct 21 |
Alice Springs | Namatjira | Minor Works | Harts Range School - Replace Fence and Signage | Tier 3 $100,000 - $500,000 | Est Mar 21 | 4 | Est May 21 |
Alice Springs | Stuart | Capital Works | SWAN Infrastructure Investment - Areyonga School | Tier 3 ($100 000 - $500,000) | Est Mar 21 | 4 | Est May 21 |
Alice Springs | Stuart | Minor Works | Alice Springs Hospital - Theatre 6 Transition to Renal Unit | Tier 3 ($100 000 - $500,000) | Est Aug 21 | 4 | Est Nov 21 |
Alice Springs | Stuart | Minor Works | Paediatric ward adolescents access | Tier 3 ($100 000 - $500,000) | Est Nov 21 | 4 | Est Feb 22 |
Alice Springs | Various | Capital Works | Replacement of Mobile Oral Health Dental Unit | Tier 4 ($500 000-$5 million) | Est Sep 21 | 4 | Est Dec 21 |
Darwin | Arafura | Capital Works | Construction - Maningrida Police Complex & Additional Housing | Tier 5 $5million and Greater | Est Feb 22 | 6 | Est May 22 |
Darwin | Arafura | Minor Works | Wildman River Station Hybrid Solar Power Generation | Tier 3 ($100 000 - $500,000) | Est Mar 21 | 4 | Est May 21 |
Darwin | Arafura | Specific Maintenance | Jabiru School - Repair Exisiting Chillers & Associated Works | Tier 3 ($100 000 - $500,000) | Est Jun 21 | 4 | Est Aug 21 |
Darwin | Blain | Capital Works | Forrest Parade School - Upgrade Outdoor Play Area | Tier 4 ($500 000-$5 million) | Est Mar 21 | 4 | Est May 21 |
Darwin | Casuarina | Capital Works | RDH - Mental Health Inpatent Unit Upgrades | Tier 4 ($500 000-$5 million) | Act Mar 21 | 4 | Est May 21 |
Darwin | Casuarina | Specific Maintenance | RDH - Building 2 - Replace CSD Trolley Washer | Tier 3 ($100 000 - $500,000) | TBA | 4 | TBA |
Darwin | Daly | Capital Works | Territory Wildlife Park - Critical Infrastructure Works | Tier 4 ($500 000-$5 million) | Act Jan 21 | 4 | Est Mar 21 |
Darwin | Daly | Capital Works | Daly River Boatramp - Carpark | Tier 4 ($500 000-$5 million) | Est Apr 21 | 4 | Est Jun 21 |
Darwin | Fannie Bay | Capital Works | MAGNT - Upgrade & Repl Heating Ventilation & Aircon | Tier 4 ($500 000-$5 million) | Act Jan 21 | 4 | Est Apr 21 |
Darwin | Goyder | Specific Maintenance | Taminmin College - Replace BER APAC Units to Block 12 & Demountable 19.3 | Tier 3 ($100 000 - $500,000) | Est Jun 21 | 4 | Est Aug 21 |
Darwin | Port Darwin | Minor Works | Government House - Terrace Upgrade | Tier 3 ($100 000 - $500,000) | Est May 21 | 4 | Est Jul 21 |
Darwin | Port Darwin | Minor Works | Parliament House - Emergergency and Exit Lighting Upgrade - Level 1 Stage 1 | Tier 3 ($100 000 - $500,000) | Act Jan 21 | 4 | Est Mar 21 |
Darwin | Port Darwin | Specific Maintenance | DSC Mould Tile Issue and Associated Works | Tier 3 ($100 000 - $500,000) | Act Jan 21 | 4 | Est Apr 21 |
Darwin | Sanderson | Minor Works | Arafura Stadium - Security Fence Upgrade | Tier 3 ($100 000 - $500,000) | Act Feb 21 | 4 | Est Apr 21 |
Darwin | Spillett | Capital Works | Construction - Berrimah Farm - Science Services Laboratory Building | Tier 5 $5million and Greater | Est Sept 21 | 4 | Est Nov 21 |
Darwin | Various | Period Contract | Darwin - State Square/Nichols Place - Landscape Maintenance for a Period of 12 Months | Tier 3 ($100 000 - $500,000) | Est Apr 21 | 4 | Est May 21 |
Darwin | Various | Period Contract | Darwin Region - Repairs and Maintenance to Airconditioning Plant and Equipment - Group 5 for a Period of 12 Months | Tier 4 ($500 000-$5 million) | Est Apr 21 | 4 | Est Jun 21 |
Darwin | Various | Period Contract | Darwin Region - Various Sites - Group 6 - Repairs and Maintenance of Airconditioning Plant and Equipment to NTG Assets for a Period of 12 Months | Tier 4 ($500 000-$5 million) | Est Jul 21 | 4 | Est Sept 21 |
Darwin | Various | Period Contract | Darwin Region - Repairs and Maintenance to Airconditioning Plant and Equipment - Group 2 for a Period of 12 Months | Tier 4 ($500 000-$5 million) | Est May 21 | 4 | Est Jul 21 |
Darwin | Various | Period Contract | Darwin Region - Repairs and Maintenance to Airconditioning Plant and Equipment - Group 4 for a Period of 12 Months | Tier 4 ($500 000-$5 million) | Est Sept 21 | 4 | Est Nov 21 |
Gove | Arnhem | Specific Maintenance | Lake Evella - Various Repairs and Maintenance | Tier 4 ($500 000-$5 million) | Est Mar 21 | 4 | Est May 21 |
Gove | Nhulunbuy | Capital Works | Construction - GDH - Upgrade Fire Safety | Tier 4 ($500 000-$5 million) | Est Apr 21 | 4 | Est Jun 21 |
Gove | Nhulunbuy | Capital Works | GDH - Fire Remediation - Nurse Call System | Tier 4 ($500 000-$5 million) | Act Oct 20 | 4 | Est Apr 21 |
Gove | Nhulunbuy | Minor Works | BBS - Umbakamba School - Replace Ablution Block | Tier 3 ($100 000 - $500,000) | Act Jan 21 | 4 | Est Mar 21 |
Gove | Nhulunbuy | Minor Works | Nhulunbuy High School - Roof Top Solar | Tier 3 ($100 000 - $500,000) | Est Mar 21 | 4 | Est May 21 |
Katherine | Arnhem | Minor Works | Numbulwar School - Upgrade Outdoor Play Area | Tier 3 ($100 000 - $500,000) | Est Apr 21 | 4 | Est May 21 |
Katherine | Arnhem | Minor Works | Ngukurr School - Roof Top Solar | Tier 3 ($100 000 - $500,000) | Est Mar 21 | 4 | Est May 21 |
Katherine | Arnhem | Minor Works | BBS - Manyallaluk School - Library/Resource Centre | Tier 3 ($100 000 - $500,000) | Est May 21 | 4 | Est Jul 21 |
Katherine | Arnhem | Minor Works | BBS - Bulman School - Kitchen | Tier 3 ($100 000 - $500,000) | Est Mar 21 | 4 | Est May 21 |
Katherine | Arnhem | Recoverable Works | Roper Gulf/NTG - Borroloola Cyclone Shelter | Tier 4 ($500 000-$5 million) | Est May 21 | 4 | Est Jul 21 |
Katherine | Daly | Minor Works | BBS - Pine Creek School - Upgrade Ablutions & Playground | Tier 3 ($100 000 - $500,000) | Est Mar 21 | 4 | Est May 21 |
Katherine | Gwoja | Minor Works | Gregory National Park Bullita Solar Hybrid Power Generation System | Tier 3 ($100 000 - $500,000) | Est May 21 | 4 | Est Jun 21 |
Katherine | Katherine | FW | Katherine East Neighbourhood Centre - External Road Works | Tier 4 ($500 000-$5 million) | Est May 21 | 4 | Est Jul 21 |
Katherine | Katherine | FW | Katherine East Neighbourhood Centre - Internal Subdivision Works | Tier 4 ($500 000-$5 million) | Est Mar 21 | 4 | Est May 21 |
Katherine | Katherine | Minor Works | KDH - Repairs and Upgrades To Fire Dampers | Tier 3 ($100 000 - $500,000) | Est Mar 21 | 4 | Est May 21 |
Katherine | Katherine | Minor Works | Katherine Police Station Refurbishment | Tier 3 ($100 000 - $500,000) | Act Feb 21 | 4 | Est Apr 21 |
Katherine | Katherine | Minor Works | KDH Women's Ward Plant Room Replace 3 X Air Handling Units | Tier 3 ($100 000 - $500,000) | Est Mar 21 | 4 | Est May 21 |
Katherine | Katherine | Minor Works | KDH - Repairs And Upgrades to Fire Dampers | Tier 3 ($100 000 - $500,000) | Est Mar 21 | 4 | Est May 21 |
Katherine | Katherine | Recoverable Works | Katherine Town Council/NTG - Leight Creek Brigde Upgrade | Tier 4 ($500 000-$5 million) | Est Mar 21 | 4 | Est May 21 |
Katherine | Katherine | Recoverable Works | Construction - Arts Trail Galley Upgrade - Mimi Arts Centre | Tier 3 ($100 000 - $500,000) | Act Jan 21 | 4 | Est Apr 21 |
Katherine | Katherine | Recoverable Works | Design- GYRACC Arts centre Upgrade | Tier 3 ($100 000 - $500,000) | Act Feb 21 | 4 | Est Apr 21 |
Katherine | Katherine | Recoverable Works | Construction- GYRACC Arts centre Upgrade | Tier 4 ($500 000-$5 million) | Est Jun 21 | 4 | Est Aug 21 |
Katherine | Katherine | Specific Maintenance | KDH Existing Specialist Clinics Upgrade Air Conditioning | Tier 3 ($100 000 - $500,000) | Act Dec 21 | 4 | Est Mar 21 |
Tennant Creek | Barkly | Capital Works | Design and Construct - Barkly Youth Justice - Construction of Modular Building to Accommodate Future Use Facility. | Tier 4 ($500 000-$5 million) | Act Feb 21 | 6 | Est May 21 |
Tennant Creek | Barkly | Capital Works | Tennant Creek High School - Juno Centre Upgrades | Tier 4 ($500 000-$5 million) | Est Apr 21 | 4 | Est Jun 21 |
Tennant Creek | Barkly | Minor Works | Alpurrurulam School - Basketball Court and Shade | Tier 3 ($100 000 - $500,000) | Est Apr 21 | 4 | Est Jun 21 |
Tennant Creek | Barkly | Recoverable Works | BRADAAG Rehab Facility | Tier 3 ($100 000 - $500,000) | TBA | 4 | TBA |
Tennant Creek | Barkly | Recoverable Works | Construction - Arts Trail Galley Upgrade - Nyinkka Nyunyu Arts | Tier 4 ($500 000-$5 million) | Est Aug 21 | 4 | Est Nov 21 |
Various | Various | Capital Works | Department of Education - Acoustic Upgrade Program | Tier 4 ($500 000-$5 million) | TBA | 4 | TBA |
Get the printable version: Building services procurement plan PDF (447.1 KB).
Last updated: 01 April 2021