Procurement plan - civil services

This page contains information about:

  • projects in preparation or tender process
  • projects in planning and design.

The procurement plan is updated monthly, dates are estimates and are subject to change without notice.

Key:

  • estimated date (Est)
  • actual date (Act).

Note: Remote contracts will be subject to access to the remote community.

Projects in preparation or tender process

RegionProgram Project descriptionTier Advertising target Advertising period (weeks) Tender commital
Alice Springs Capital Works Napperby Road - Lift and Re-sheet Chainage 32.4 - 40.1 kilometres Tier 4 $500,000 - $5M Act Dec-19 4 Est Mar-20
Alice Springs Capital Works Willowra Road - Lift Pavement at Chainage 69.9 - 75.3 kilometres Tier 4 $500,000 - $5M Act Dec-19 4 Est Mar-20
Alice Springs Capital Works Ernest Giles Road - Lift, Gravel Re-sheet and Improve Drainage chainage 78.46 - 100.33 kilometres Tier 4 $500,000 - $5M Act Dec-19 4 Est Apr-20
Alice Springs Capital Works Tanami Road - Shoulder Widening between Chainage 7.7 - 19.8 kilometres Tier 4 $500,000 - $5M Act Dec-19 4 Est Mar-20
Alice Springs Capital Works Lasseter Highway - Strengthen and Widen Chainage 222 - 226 kilometres Tier 3 $100,000 - $500,000 Act Feb-20 4 Est May-20
Alice Springs Capital Works Tjukaruru Road - Upgrade chainage 12.7 - 15 kilometres Tier 4 $500,000 - $5M Est Apr-20 4 Est Jul-20
Alice Springs Capital Works Roads of Strategic Importance - Select Upgrades on the Tanami Road Tier 4 $500,000 - $5M Est Mar-20 4 Est Jun-20
Alice Springs Cyclical Maintenance Alice Springs Region - Repairs and Maintenance of Bus Stops and Shelters for a Period of 36 Months Tier 4 $500,000 - $5M Act Dec-19 5 Est Mar-20
Alice Springs Cyclical Maintenance Alice Springs Region -  Traffic Signals and Intelligent Transport Systems Maintenance for a Period of 36 Months Tier 3 $100,000 - $500,000 Act Mar-20 4 Est May-20
Alice Springs Cyclical Maintenance Alice Springs Region - Road Inspections and defects Recording and Asset Data Collection for a Period of 36 Months Tier 4 $500,000 - $5M Est Apr-20 4 Est Jun-20
Alice Springs Minor New Works Tanami Road Reformation and Reconstruction of Shoulders Chainage 105 - 117 kilometres Tier 3 $100,000 - $500,000 Act Dec-19 5 Act Feb-20
Alice Springs Minor New Works Various Bus Stops - Type 15 Bus Shelter Upgrades Tier 3 $100,000 - $500,000 Act Feb-20 1 Est Apr-20
Alice Springs Minor New Works Installation Of Electronic Road Advice / closure Signs Tier 3 $100,000 - $500,000 Act Feb-20 5 Est Apr-20
Alice Springs Minor New Works Yulara Camp Ground - Turning Lane Works Tier 3 $100,000 - $500,000 Act Jan-20 4 Act Feb-20
Alice Springs Specific Maintenance Southern Region - Bituminous Resurfacing Of Various Roads And Airstrips Tier 3 $100,000 - $500,000 Act Jan-20 4 Est Mar-20
Darwin Capital Works Tiger Brennan Drive at Berrimah Road Intersection and Berrimah Road - Asphalt Resurfacing and Pavement Replacement Various Sections Tier 4 $500,000 - $5M Act Feb-20 3 Est May-20
Darwin Capital Works Dorat Road - Culvert Upgrade and Protection Works Tier 3 $100,000 - $500,000 Act Mar-20 2 Est Apr-20
Darwin Capital Works Mermaid Circuit Upgrade from Unsealed to Sealed Chainage
0 - 1.1 Kilometres
Tier 4 $500,000 - $5M Est Apr-20 4 Est Jun-20
Darwin Capital Works Kakadu Highway - Install Approach Guard Rails at Little and Big Ellie Creek Crossing Tier 3 $100,000 - $500,000 Est Apr-20 2 Est Jun-20
Darwin Capital Works Stuart Highway/Chinner Road - Intersection Upgrade Tier 3 $100,000 - $500,000 Est Apr-20 4 Est Jun-20
Darwin Capital Works Bagot Road - Landscaping Upgrade Tier 4 $500,000 - $5M Est Apr-20 4 Est Jun-20
Darwin Capital Works Stuart Highway - Install guardrails at various locations between Temple Terrace and Virginia Tier 3 $100,000 - $500,000 Est Apr-20 4 Est May-20
Darwin Capital Works Litchfield Welltree Station Access - Installation of Concrete Margins and Protection Works At Chainage 0.2, 2.5, 4.3, 4.9, 5.6 and 15.2 kilometres Tier 3 $100,000 - $500,000 Est Apr-20 2 Est May-20
Darwin Capital Works McMillans Road / Mueller Road - Intersection Upgrade Tier 4 $500,000 - $5M Est Apr-20 2 Est May-20
Darwin Capital Works Elrundie Avenue / Driver Road Intersection Upgrade Tier 3 $100,000 - $500,000 Est Apr-20 4 Est Jun-20
Darwin Capital Works Kakadu Highway - Install Approach Guard Rails at Jim Jim Creek Tier 3 $100,000 - $500,000 Est Jun-20 2 Est Jul-20
Darwin Capital Works Kakadu Highway - Install Approach Guard Rails at Nourlangie Creek Tier 3 $100,000 - $500,000 Est Jun-20 2 Est Jul-20
Darwin Capital Works Illawarra Road Lift, Reform and Drainage Improvements Chainage 0 - 7.8 Kilometres Tier 4 $500,000 - $5M Est Mar-20 4 Est May-20
Darwin Capital Works Temple Terrace - Landscaping Upgrade between Stuart Highway and Roystonea Avenue Tier 4 $500,000 - $5M Est Mar-20 4 Est May-20
Darwin Capital Works Roads of Strategic Importance - Port Keats Road upgrading Saddle Rail Creek Crossing Tier 5 $5M and Greater > $20M Est Mar-20 4 Est May-20
Darwin Capital Works Roads of Strategic Importance - Upgrade and Seal Horsnell Road to Improve the Productivity of the Mango Industry - Package 1 Tier 4 $500,000 - $5M Est Mar-20 4 Est May-20
Darwin Capital Works Roads of Strategic Importance - Upgrade and Seal Chibnall Road to Improve the Productivity of the Mango Industry - Package 2 Tier 4 $500,000 - $5M Est Mar-20 4 Est May-20
Darwin Capital Works Roads of Strategic Importance - Upgrade and Seal Mocatto Road to Improve the Productivity of the Mango Industry - Package 3 Tier 4 $500,000 - $5M Est Mar-20 4 Est May-20
Darwin Capital Works Trower Road and Sabine Road Intersection - Road Safety Improvements Tier 3 $100,000 - $500,000 Est Mar-20 2 Est May-20
Darwin Capital Works Maningrida-Ramingining Road - Seal Road Chainage 0.4 - 1.6 Kilometres Tier 4 $500,000 - $5M Est May-20 4 Est Jul-20
Darwin Cyclical Maintenance Darwin Region -  Period Contract -  Maintenance Of Guardrails For A Period Of 36  Months Tier 3 $100,000 - $500,000 Est Mar-20 4 Est May-20
Darwin Cyclical Maintenance Darwin Region -  Period Contract -  Miscellaneous Concrete Works For A Period Of 36 Months Tier 3 $100,000 - $500,000 Est Mar-20 4 Est May-20
Darwin Cyclical Maintenance Darwin Region - Road Inspections and Defects Recording and Asset Data Collection for a Period of 36 Months Tier 4 $500,000 - $5M Est Mar-20 4 Est May-20
Darwin Minor New Works Various Urban Locations - Upgrade Bus Stops - Package 1 Tier 3 $100,000 - $500,000 Act Jan-20 2 Est Mar-20
Darwin Minor New Works Henry Wrigley Drive Mararra Basin - Construct Car Park Tier 3 $100,000 - $500,000 Act Jan-20 3 Est Mar-20
Darwin Minor New Works Palmerston - Elrundie Avenue Chainage 0.59 - 1.43 kilometres upgrade to Asphalt Surface Tier 3 $100,000 - $500,000 Act Mar-20 1 Est Apr-20
Darwin Minor New Works Various Urban Locations - Upgrade Bus Stops - Package 2 Tier 3 $100,000 - $500,000 Act Mar-20 2 Est Apr-20
Darwin Minor New Works Trower Road - Outbound Lane Modification Between Rothdale Road and Parer Drive Tier 3 $100,000 - $500,000 Act Mar-20 2 Est Apr-20
Darwin Minor New Works Casuarina Intersection - Supply and Install Impact Absorbing Bollards and footings along Bradshaw Terrace at the Bus Interchange Tier 3 $100,000 - $500,000 Est Apr-19 4 Est Jun-19
Darwin Minor New Works Stuart Highway - Replace HPS Streetlighting with LEDs Tier 3 $100,000 - $500,000 Est Mar-20 2 Est Apr-20
Darwin Minor New Works Palumpa Airstrip Fencing Upgrade Tier 3 $100,000 - $500,000 Est Mar-20 2 Est Apr-20
Darwin Minor New Works Stuart Highway - Remove Existing and Install New Guardrail Between Chainage 170.9 and 171.1 kilometres Tier 3 $100,000 - $500,000 Est Mar-20 2 Est Apr-20
Darwin Minor New Works Abala Road - Realign Existing Path to Rear of Three Bus Stops Tier 3 $100,000 - $500,000 Est Mar-20 3 Est May-20
Darwin Specific Maintenance Elizabeth River Bridge Joint Expansion Replacement Tier 3 $100,000 - $500,000 Est Mar-20 4 Est May-20
Darwin Specific Maintenance Stuart Highway - Minor Pavement Rehabilitation in various locations Tier 3 $100,000 - $500,000 Est Mar-20 2 Est May-20
Darwin Specific Maintenance Stuart Highway - Shoulder Rehabilitation Various Locations Tier 3 $100,000 - $500,000 Est Mar-20 2 Est May-20
Darwin Specific Maintenance Berrimah Road - Pavement Rehabilitation Tier 3 $100,000 - $500,000 Est May-20 2 Est Jun-20
Gove Capital Works Elcho Island - Aerodrome Apron Extension and Secure Compound Construction Tier 4 $500,000 - $5M Act Oct-19 6 Est May-20
Gove Capital Works Central Arnhem Road - Upgrade and Seal (Goyder River Bridge) Chainage 363.64 - 377.04 kilometres Tier 4 $500,000 - $5M Est Jun-20 4 Est Aug-20
Katherine Capital Works Gorrie Dry River - Gravel Resheet in various sections Tier 3 $100,000 - $500,000 Act Feb-20 3 Est May-20
Katherine Capital Works Carpentaria Highway - Strengthening And Widening Between Chainage 109 - 114.5 Kilometres Tier 4 $500,000 - $5M Act Jan-20 4 Act Mar-20
Katherine Capital Works Central Arnhem Road (Beswick Township) - Shared Use Path Tier 3 $100,000 - $500,000 Act Mar-20 4 Est May-20
Katherine Capital Works Buntine Highway - Upgrade and Seal Chainage 230.1 - 237 kilometres Tier 3 $100,000 - $500,000 Est Apr-20 4 Est Jun-20
Katherine Capital Works Upgrade and Seal Chainage Buntine Highway 3 - 4.2 kilometres and Victoria Highway 82 - 87 tres Tier 5 $5M and Greater > $10M Est Apr-20 6 Est Jun-20
Katherine Capital Works Bauhinia Property Access - Construct Invert at Chainage 19.4 - 19.5 kilometres Tier 3 $100,000 - $500,000 Est Apr-20 2 Est May-20
Katherine Capital Works Old Humbert Road - Construct Multi-Barrel Culvert at Sandy Creek Tier 4 $500,000 - $5M Est Apr-20 3 Est May-20
Katherine Capital Works Central Arnhem Road - Upgrade and Seal (Beswick) Chainage 59.8 - 66.0 kilometres Tier 4 $500,000 - $5M Est Mar-20 4 Est May-20
Katherine Cyclical Maintenance Katherine Region - Road Inspections and Defects Recording and Asset Data Collection for Period of 36 Months Tier 4 $500,000 - $5M Est May-20 4 Est Jul-20
Katherine Minor New Works Kildurk Station (Amanbidji) Airstrip Widen Taxiway To 10.5m Tier 3 $100,000 - $500,000 Act Feb-20 3 Est Apr-20
Katherine Minor New Works Stuart Highway / Emungalan Road Intersection - Upgrade Truck Stop Tier 3 $100,000 - $500,000 Act Feb-20 1 Est Mar-20
Katherine Minor New Works Carpentaria Hwy - New Truck Parking Bay at Chainage 270.2 Kilometres and Shoulder Rehabilitation and Seal Widening Tier 4 $500,000 - $5M Act Jan-20 4 Act Mar-20
Katherine Minor New Works Buntine Highway - New Truck Parking Bay Inbound Chainage 164.9 Kilometres Tier 3 $100,000 - $500,000 Est Mar-20 3 Est May-20
Katherine Specific Maintenance Victoria Highway - Minor Pavement Rehabilitation in Various Locations Tier 3 $100,000 - $500,000 Est Mar-20 3 Est Oct-20
Tennant Creek Cyclical Maintenance Tennant Creek Region - Road Inspections and Defects Recording and Asset Data Collection for a Period of 36 Months Tier 4 $500,000 - $5M Est May-20 4 Est Jul-20
Tennant Creek Minor New Works Stuart Highway - Construct Slip Lanes and Turning Treatment for Wauchope Roadhouse at Chainage 1,104 Kilometres Tier 3 $100,000 - $500,000 Act Feb-20 4 Est Apr-20
Tennant Creek Minor New Works Elliott - Extend Concrete Footpath Between Buchanan And Mcrae Street Tier 3 $100,000 - $500,000 Act Feb-20 3 Est Apr-20

Projects in planning and design

RegionProgram Project descriptionTier Advertising target
Alice Springs Capital Works Plenty Highway (Outback Way) - Upgrade and Seal Various Sections Tier 5 $5M and Greater Q2 2020
Alice Springs Capital Works Roads of Strategic Importance - Select Upgrades of Maryvale Road Tier 4 $500,000 - $5M Q3 2020
Alice Springs Capital Works Tjukaruru Road (Outback Way) - Upgrade and Seal Various Sections Tier 5 $5M and Greater  Q2 2020
Alice Springs Capital Works Schwarz Crescent Upgrade Tier 5 $5M and Greater Q2 2020
Darwin Capital Works Arnhem Link Road Upgrades - Upgrade Various Sections on Maningrida Access Road And Maningrida Ramingining Road Tier 4 $500,000 - $5M Q1 2021
Darwin Capital Works Arnhem Link Road Upgrades - Oenpelli Road Upgrade and Seal Select Sections Near Red Lily Lagoon Tier 4 $500,000 - $5M Q1 2021
Darwin Capital Works Coolalinga Traffic Management Tier 5 $5M and Greater Q3 2020
Darwin Capital Works Stuart Highway Upgrade - Pinelands To Industrial Precinct Access Tier 4 $500,000 - $5M Q3 2020
Darwin Capital Works Wadeye Barge Landing Upgrade Tier 4 $500,000 - $5M Q2 2020
Gove Capital Works Central Arnhem Road - Upgrade and Seal Chainage 250.4 - 254.5 kilometres Tier 4 $500,000 - $5M Q1 2021

Get the printable version: procurement plan - civil 2019-2020 PDF (183.2 KB)

Last updated: 27 March 2020

Share this page:

Was this page useful?

Describe your experience

More feedback options

To provide comments or suggestions about the NT.GOV.AU website, complete our feedback form.

For all other feedback or enquiries, you must contact the relevant government agency.